This Adventurous Age

Adventures travelling and working around Australia.


Leave a comment

2006 Travels November 28

TUESDAY 28 NOVEMBER     RV1

Mid 40’s and very steamy after yesterday’s storms.

In the absence of anyone even vaguely resembling management on site, I had been instructed to sign off, on the company’s behalf, on Milestone 4. The FMG head honcho from Hedland arrived on site in the morning, and we duly signed the document. My signature was worth something like $6 million to the company! When I – reluctantly – took this job on, had not envisaged anything like that responsibility! For that matter, had not envisaged most of what I’d ended up doing…….

11-25-2006 rv1 aerial

RV1 as it would look in another few weeks. Gaps at ends of Pods for possible extra dongas

There was much cleaning up needed after the storm. The wind had redistributed quite a lot of loose stuff. John had to re-do safety barriers blown down in the storm.

John took the Acco to Hedland with a load for the tip. A flying stone broke the Acco windscreen on the way back. Then he went to RV2 with a load of materials for there, on the Canter. Then he had to drive back to Hedland for the evening plane. This was two hours late, so he was very late getting back. When this happened, as it did regularly, I was in the habit of getting a plate of cold dinner makings – salads and meats – and taking it back to our rooms. Sometimes, he was able to get a meal in Hedland anyway, before starting back – it really depended on what whoever he’d picked up wanted to do.

The shower repairers said they’d finished here and went on to RV2 to do some that had the same problems there.

The guy who wanted my office signed the lease contract.

12-03-2006 wendy at work

I spent some time on the phone, trying to chase up documentation I thought was needed for the Building Registers, from the SPQ manufacturers in Perth.

At RV2, there was a hunt for the RV1 disabled toilet that was supposed to have been transported there – which in turn was to replace our original one, which K had installed down there! K swore the new one was not there – but then he said that last time. Mystery of the disappearing toilets.

S drove BB to Newman to catch a plane to wherever he was going next. She could be spared for several hours – the men could not.

We were now into our last week here! Hard to believe……


Leave a comment

2006 Travels November 27

MONDAY 27 NOVEMBER     RV1

Mid 40’s. Humid in the morning.

It was getting a bit quiet here on the work front – today only two company men, us and two electricians who did turn up.

It was discovered that the instant hot water service in the main office – which was not working and was the subject of regular complaints to me by Spotless manager, (who had tried to fix it himself) – was in fact, not wired up! That had been overlooked by the electrician at the time.

Because of the change of mind about that damned office shutter. I had to phone the shutter company and explain we no longer wanted it. But apparently there had been some change of mind about who was building it and I faxed the design diagram that A had done, to the Perth company that built our SPQ’s, to get them to make the wall up – on BB’s instructions. It might still take two or three weeks, but I ordered it to be delivered to RV1 then.

I had to phone the company that installed the air cons to see if they would agree to a local firm fixing some that had been found to be faulty, as rooms were occupied.

I chased up a copy of the letter that BB had written to FMG about the electrical spikes stuffing up some of the gear in the place – needed it for the Document Register!

I spent much of the day putting together the Building Registers. Without R here to guide me, I was rather flying blind on that. It seemed a hell of a lot of material, but I had decided to put in everything that could possibly be relevant. Times four!

Resize of 11-26-2006 donga pod

Almost finished…..

Two men came in from the Perth building company to fix the weak shower bases. They did not seem real happy…..

The missing kitchen/mess curtains – which we had hunted for previously – and for which V had ordered replacements made in Alice Springs – were found in one of the containers, after all – at RV2! Who the hell put them there – and when? I had never even set eyes on them before. Had to have been K or S…..

So there would be a double lot of curtains, as the new ones were already in transit. Guess a use would be found for them somewhere……

John had to do an airport run in the morning to get the shower fixers. He had a tip run in the afternoon. He also had to buy portable gas BBQ’s for each village, gas bottles for those, fire hydrant hooks and fire signs for RV2, from the fire service company in Hedland.

The main camp generators failed twice today, so the camp water supply ran out.

At RV2, where K was back but BB still there too, one of the men went off sick and would not be fit again till next year – heat stress related, apparently. Someone on the ditch digger broke the pool pipes and that took all day to fix! That figured – K was back! There were bushfires within 2kms of the site, so the fire break was made much bigger. They were laying pipes from their bore field to the camp – still no water on there.

Resize of 12-15-2006 at RV2 IMG_0266

Distant burnt hills at RV2

I had an email from boss lady. After conversation with BB at RV2, she instructed that Milestone 4 was to be signed off on today. Milestone 5 – full completion of RV1 – was to be signed when the sports court was complete, after the surfacing company was here on December 11 – N would co-ordinate that from RV2. Two extra men would come up from RV2 to work on the final punch list of defect fixing.

Her great news was that R was fit again. He was to fly to SA tomorrow, to relieve the Project Manager at the camp construction site there and get a handle on that project. Then, in about ten days, he would fly here for the final total sign off of RV1 and to get an overview of RV2 progress, before flying back to Darwin in time for Xmas. I was so pleased to hear he was OK.

She instructed that we were to work through this week and wind up the office in an orderly fashion by December 4, after which we would leave. She asked that we be on standby to fly back to RV2, in January, if needed. That needed to be decided by K and R before Xmas, depending on how far along RV2 was. Seemed like S had definitely had enough of mixing it with the workers!

December 20 was to be the travel day for all the remaining company workers, to go home for their Xmas break.

So – we were actually finishing up a bit earlier than I’d expected – the next few days could be quite a rush. But it was great that we would have time to drive home comfortably before Xmas. But we might become real FIFO workers, for a little while, next year! More money!

There had been a really nasty cloud build up through the humid day, then about 5pm a massive storm broke, with strong wind gusts, thunder, lightning and rain. A deluge, in fact. The lay down  area/carpark turned into a sea of red water and mud.

Resize of 11-27-2006 storm 1

Resize of 11-27-2006 storm 11

Resize of 11-27-2006 storm 12

11-27-2006 The Rain 4

Raindrops keep falling……on my lens

That lasted until about 9pm. Quite spectacular. This really was raw and elemental country……

11-27-2006 Aftermath


Leave a comment

2006 Travels November 26

SUNDAY 26 NOVEMBER     RV1

Mid 40’s today.

We had been asked to work, instead of having a day off, such was the pressure to get everything finished. That would make for a bigger pay packet next time round.

Once again, the electrician had disappeared off home to Hedland – I wondered how much it had to do with Saturday night – so there was no one here from the electrical company. The Pod 3 power points were still unfinished.

The comms company gave Spotless a demonstration of how the comms were to work. TV came in via satellite, of course, as did internet and phones. TV was cabled from the central control point to all the SPQ rooms and the wet mess.

12-01-2006 Television Dish

John and the comms man did the final check of the signal strength of the comms system and John prepared a spreadsheet to be given to Spotless – and a copy for my files too.

Resize of 12-05-2006 leaving RV1 last view

TV system receivers on the end of each SPQ donga

We handed over all the Pod 3 keys to Spotless. John and the second manager did a final Pod 3 punch list. There were still not enough bloody door locks though!

The pool company finished up here and went on to RV2.

12-01-2006 Pool Fenced

A company worker came from RV2 to do some repair work to some verandas here. There was a lot of to-ing and fro-ing between the two sites now.

The bulk of the company’s workers at RV 2 had been taken out for the day, by BB, on a boat fishing trip, from Hedland. N went, but not S! Boys only….Word was that they’d had an enjoyable day. I suspected it would have been a rather boozy one! With conditions as tough as they were down there, morale boosting exercises were a good idea. That was why BB had wanted the bongo bus…..

Resize of Wait till I tell Matt


Leave a comment

2006 Travels November 25

SATURDAY 25 NOVEMBER     RV1

Low 40’s and humid.

The company only had two men working here now – and us. The electrical work was progressing – slowly, as usual! Four men from the pool company were working on that. Two men from the comms company were installing TV’s and the central broadcast system for same.

11-25-2006 Pool Fence being Erected2

Working on the pool

The mechanics company came to check and service vehicles, then go on to RV2 to do the ones there. They’d had good business from us, but it was invaluable having them come to the site to do servicing and repairs.

The forklift was U/S – having been borrowed – without permission of course – by one of the railway building companies on site. Mechanic said he would have to get in parts for it. Other site occupants raiding our gear containers and equipment had become a real problem.

Our two men painted the wet mess beer garden deck. Did more cleaning up about the place. They had removed a section of the deck wall and hoped that would be sufficient to pass muster.

11-25-2006 Alan and Peter Painting Wet Mess Floor

Painting the decking floor of the wet mess

John collected BB from the morning plane, then took the Acco to RV2 with their pool shed and fence and came back with a bobcat borrowed from there, and some cement mix.

Apparently, BB had been in some discussion with FMG, who were now concerned that the 280 rooms would not be sufficient for the needs of the railway builders. Our company might have to commission and install eight more SPQ dongas at each village – there had been some provision for these on the original plans. That would add 32 more beds to each Village. That work could not happen before next year though. BB said he thought they might start hot bedding – when I looked mystified he explained that meant working in  shifts so two men used the same bed. My mind boggled – I just hoped they changed the sheets in between. All part of the great sense of urgency that was now pervading the place.

BB did a walk round of the camp, with P, and made a new punch list of all that still needed to be done. He and A had a talk about the Spotless security screen and it was decided that A would build it on site. Then BB took the bongo bus to go to RV2.

 


Leave a comment

2006 Travels November 24

FRIDAY 24 NOVEMBER    RV1

Low 40’s.

I packed up R’s stuff in the office and dispatched it to Darwin on the company truck that was returning there. That same truck would load up R’s vehicle at Broome airport and truck it back to Darwin. A sad ending – we didn’t get to say goodbye. I hoped he would fully recover from whatever was ailing him.

John took a load with the Canter to the tip in the morning and brought back pool fencing. He had reported that the cab was getting extremely hot, took it to the mechanic in Hedland, who found a loose panel between the cab and the engine bay!

Resize of 11-24-2006 john off to tip 1

Off to the tip, with the Canter

In the afternoon, he took the Acco to Hedland and picked up the pool shed destined for RV2.

There was a steady movement of our surplus equipment and stuff to RV2. At least, I hoped it WAS surplus!

The men had commenced clearing and packing up the lay down area. This would become a part of the large car park area for camp residents.

11-18-2006 Car Park now with lots of cars

Already a number of vehicles were being parked in the laydown area

Once again, the electrical company work was holding up other progress. The electricians had been missing in action this morning and only turned up in the afternoon. The Pod 3 TV’s could not be properly installed until the power points had been done.

Got word that the missing locksets for the Pod 3 doors would finally be coming – with BB from Perth, on Saturday.

About a week ago, I was approached by a guy from one of the companies that would be working on the railway line build, wanting to know if my site office would be available for them to hire. He was temporarily working out of one of the other assorted contractors’ offices that firms had set up at the side of the camp area. HO approved of that and said they would prepare a contract. It arrived today, for him to sign. So my office would not now be moved, but would stay and have to have services hooked up to it – water and camp power.

11-18-2006 Safety Shower

Safety shower installed outside the chemical store donga – a very pre-loved building

Also word came that the company HO had chosen could not deliver the roller shutter for the Spotless office until February. What now?

We appeared to have lost a batch of road signs that R had borrowed from a survey company, a while ago.

The semi took the trench digger, bobcat and concrete mixer to RV2.

Spotless was hassling me about a new griller that was required for the kitchen and whether it had been ordered – in turn, I was hassling V in HO about the same thing!

K came back from leave, so would be back at RV2 now.


Leave a comment

2006 Travels November 23

THURSDAY 23 NOVEMBER     RV1

There were storms this morning, but it was still about 40 degrees, just more humid. We were getting some really interesting skies, that had me reaching for the camera.

11-23-2006 Storm Clouds 2

BB and FMG had agreed that we were to source and fit a roller/security shutter across the counter in the site office. There was nothing like that in the original plan, but the Spotless manager had been jumping up and down about it. I would not have thought his paperwork was really so high security! So I spent a lot of the day on the phone, trying to arrange for quotes for that.

11-23-2006 Spotless Office where security mess is required amended

Office area where mesh security roller screen required

The rest of the Pod 2 rooms, and all of the Pod 3 ones, were handed over to Spotless – apart from 16 unsecured rooms where we were waiting on missing locksets. Big progress!

The Acco tip truck had a cracked windscreen ,after John did a tip trip with it today. I doubted it was now roadworthy.

HO had come up with the figures that we were charging FMG $250 per tip trip, plus tip charges, as contingency. Boy, that was going to add up!

There was a really interesting cloud roll formation today. I knew such phenomena happened up in the Gulf country – the famed Morning Glory cloud – but did not know they happened elsewhere. I really should try to read up on meteorology a bit more – as well as on identifying little reptiles!

Resize of 11-23-2006 cloud roll 4

Resize of 11-23-2006 parking area

Cloud roll over the parking area and John’s Acco tip truck

The Hedland FMG boss phoned to say that they now had approval for us to dig a temporary tip hole at RV1. Fine – BUT – we no longer had any digging gear on site. It had all gone south.

N and S returned from their break.

R had not returned from his break yet, having been away ten days. It was rumoured that he would not be returning because he was having some kind of breakdown. That would not have surprised me – he was under so much pressure here. Pity, because I thought he was a really great guy.

Resize of 11-23-2006 cloud roll 3


Leave a comment

2006 Travels November 22

WEDNESDAY 22 NOVEMBER     RV1

Low 40’s.

There were only 4 company men working here now, 5 at RV2, with some subbies at both sites.

Had a minor vehicle collision on site this morning. P’s son was going out on the morning plane, but for some reason before he left, went to jump start his dad’s vehicle,  still in gear. It jumped forward and hit the Canter. Minor damage. Unfortunately, the FMG Safety Officer, from Hedland, who we’d had some issues with, every time he visited the site, was here at the time. He was an officious little man whom nobody liked. He then saw the lad working on the forklift for a few minutes, whilst waiting for John, wearing his casual gear and thongs. Safety man reported it, of course. So A, who was in charge here, had to deal with the lad. I had to deal with the FMG man – lucky me!

11-26-2006 P1000658

Another variety of reptile around camp – funny shaped little fellow.

J took P’s son to the morning plane and then collected R and M and another of the company men, from the midday plane. Then he had to go back to Hedland to collect two subbies from the afternoon plane, which was late. So he was away for much of the day, and booked up some extra work hours at night.

The company guy John collected from leave, was told to stay at RV1 to help with the tail end incidentals. So he had to take the Canter to RV2 to collect his gear. While he was down there, he fixed the phones – which had gone u/s again – following instructions given to him by the comms company before he left RV1.

M and R were to move to RV2 now – more cleaning and unpacking for M.

There was a gas problem with the vegetable coolroom refrigeration unit.

A – in charge at RV1 – was convinced the beer garden would not meet the Shire regulations, and that some wall would have to be removed.

The temporary bubbler cooler units installed in the ice room now appeared to have worked to cool the water enough for the three ice machines to now be churning out sufficient ice cubes. A win, at last!

Resize of 11-18-2006 dusk 5


Leave a comment

2006 Travels November 21

TUESDAY 21 NOVEMBER     RV1

Mid 40’s. The heat just went on and on.

Lots of oddments were being worked on about the camp.

The roller door for the wet mess would be made in Adelaide and a transport company would bring it here.

Tonight, seven of the Pod 2 rooms were used by Spotless – the first of the rooms in that Pod to be used, apart from ours.

11-27-2006 Fleetwood Made up bed.

SPQ unit made up for occupancy

The sewer firms was training the two bosses about the sewer and water. Bet they loved that!

A company would be in to surface the sports court here about 11 December, and at RV2 about 18th.

Resize of 11-29-2006 RV1 aerial 23

Sports court ready for surfacing – taken from high up

I had to call the Shire Inspector to clarify how much open space – as opposed to walls – was needed for the beer garden – because of people smoking. Could be an issue because the decks came with a certain amount of wall holding up the roof! If they head to be replaced with open beams or something, that would be a big hold up.

11-23-2006 Beer garden Wet Mess

Beer garden decks just placed – too much wall?

John did two trips to Hedland. When these involved the Acco tiptruck, it got pretty uncomfortable because it had no cooling system. At least the Bongo Bus had air con.

The gensets went down again in the morning, for a while and again in the afternoon. I could see more breakdowns of electrical equipment looming! Spotless was concerned about how the gensets would cope when there was a full camp, instead of only a third full,  as now. They were also worried about what the fuel usage by them would be then. Thank God that bit of equipment was nothing to do with our contract.

I went down to RV2 again, to do the office work down there. Quite enjoyed the drive – I found the country interesting, although many wouldn’t. The phones and modems appeared to be working alright there, now.

BB went to Perth, with P.  Two of the more experienced workers were left in charge at each site. Several of the men were on leave break from RV2.

At RV2 they had to order in two big truck loads of water to fill the pool because the water was not connected there yet. One of the men came down with heat stroke.

A problem was found at RV2. All the newly installed office modules had to be re-lifted to comply with correct step height. It took 3 men 6 hours to do that. The electrical conduits would have to be altered as a result. This was another K stuff up – he should have realized that the ground at RV2 was more sloping than at RV1 which affected the steps needed.

11-26-2006 Mr NT Link 2

Reptiles were adapting to the camp – nice home under that path!

 


Leave a comment

2006 Travels November 20

MONDAY 20 NOVEMBER     RV1

Over 45 today, and there were oppressive storms late in the day.

A lot happened yesterday.

A man from the electricians had to make a special trip up from RV2, for a while, to sort out the Pod 2 rooms that had electrical issues and get them ready to occupy. It seemed that B, the man from that company who was normally here all the time, had taken it upon himself to take the weekend off, without telling anyone. The SPQ building in Pod 2 that had the problems had already had six hours of man time spent trying to sort it out and the problem was still not found.

After all that, Spotless decided to cancel the hand over ceremony and its forty guests. Good!

Someone got the Landcruiser tyres fixed yesterday.

The kitchen fence was finished and those men left.

11-23-2006 Fenced area back of mess

Fenced yard around the kitchen loading dock and cold units

The gym was declared set up and operational, but was missing two gym mats. So today I had to phone HO to find some and get them to us, somehow.

12-02-2006 Gym Equipment

Some of the equipment int the gym

Spotless had occupation of the main part of the wet mess, but the roller door that would block off the bar counter when required was missing, and there was still some other work ongoing.

11-25-2006 Wet Mess and TV

Inside the wet mess

I ordered a roller blind thing from a company in Alice Springs.

From the quarry company I was told to order shingle stone – a 12 metre side tipper load – for “landscaping”.

One of the men had done a tip trip on Sunday.

A SPQ donga that was still at Fly Camp was moved to RV2. Down there, they also received 4 office modules and 2 kitchen modules.

Two of the company workers who had been based here were moved permanently to RV2.

I inducted 4 pool company men, here to install the pool, and a man here to install the TV system.

The kitchen compressor unit broke down again last night. The drinks display fridge in the wet mess was not working properly. There were just too many electricals related problems it seemed to me! The cooling man came and fixed the drinks fridge but said we needed yet another new kitchen compressor.  He was sure the repeated failures were due to power fluctuations.

John went to Hedland to return the light tower now that the cementers had finished doing the incidental paths. He also took in some of the semi’s tyres to be repaired.

The sewer company man was working on the sewer and water plants. He said they would train the Spotless managers in their workings. Why didn’t they do that in the first place?

A problem was emerging that some of the smoke alarms installed in the SPQ rooms were going off for no apparent reason. The heat? It was making the Spotless managers really cross.

John had an unusual and unforeseen job today, in amongst his two trips to Hedland. Last Thursday, when BB overnighted here, he nearly went through the base of the shower recess in his bathroom. He was not happy and ordered that every one be checked. So John and the Spotless second manager went round and checked them, by bouncing up and down in each shower. BB was a rather large man, but…… Of the 232 showers, 44 were lacking  bracing. BB was still running the show at RV2, so he got to deal with the manufacturers, about that, for which I was grateful.

11-27-2006 Fleetwood shower

I was starting to dream of having a cool – or cold – shower! No such animal in these parts.


Leave a comment

2006 Travels November 19

SUNDAY 19 NOVEMBER     RV1

Hot. There was an early thunder and lightning storm and it was really humid.

It was our day off. We’d now been on site for nine weeks. In some ways, it seemed to have gone fast but at the same time seemed  like ages. Had we been normal FIFO staff with the company, we’d have been out on break twice now, for a week each time. But apart from our few days at Eighty Mile Beach, we’d stayed here.

Did the washing – nice to have access to a proper laundry with lots of machines, and not have to queue for use.

Apart from that, just relaxed around our rooms and the van.

At one stage, earlier in our time here, when it was a bit cooler, we’d debated whether we should try to visit Karijini National Park on our day off, and do some walking there. But it was over 200kms to drive, each way, so neither of us could motivate ourselves to do that. Had it been closer……

Resize of 11-18-2006 dusk 3